CONSTRUCTION CONTRACT
The site is located on Johns Lane West, Dublin 8. John’s Lane West project consisted of the construction of a sheltered-housing, residential apartment development, comprising 31 units. comprising 16 No. one-bedroom, 10 No. two-bedroom and 5 No. three-bedroom apartment units.
PROPORTION OF PROJECT UNDERTAKEN
All of the precast, including walls, floors & Stairs
FUNCTION / ROLE
We provided a full design/coordination/detailing service for the precast elements from receipt of the Architects and Engineers drawings. Once this was done and approved by the Client, we then manufactured the elements in our carousel factory, delivered them to site and fitted the panels with our own crews plus we also had full time project management based on site.
PRECAST ELEMENTS REQUIRED
200mm TW
250mm TW 70mm Omnia floors PC Columns & Beams |
VALUE
Value of firm’s commission/contract: €880k
Construction Contract value: €15m
DESIGN TEAM
Architect: C.J. Falconer & Asscoiates
Engineer: Nicholas O’Dwyer
GENERAL
Contracting Authority name: Duggan Brothers