CONSTRUCTION CONTRACT
Re-development of the existing Ashling Hotel in Dublin.
A precast concrete frame was provided from the first floor transfer slab level for the entire hotel building. We constructed a complete shell from the first floor walls to the seventh floor including the roof slab. All transfer structures and beams were provided in our precast system above the first floor slab level. All services and cast in items are also coordinated with the walls and slabs.
PROPORTION OF PROJECT UNDERTAKEN
Whole precast shell 1st floor to the 7th floor, walls and floors.
FUNCTION / ROLE
We provide a full design/coordination/detailing service for the precast elements from receipt of the Architects and Engineers drawings. Once this is done and approved by the Client we then manufacture the elements in our carousel factory, deliver them to site and install the units. We also supervise and control the erection to ensure programme and quality is met.
PRECAST ELEMENTS REQUIRED
VALUE
Value of firm’s commission/contract: €1.2m
Construction Contract value: €50m
DESIGN TEAM
GENERAL
Contracting Authority name: Ellen Construction Ltd.