Projects

New Distribution Centre for ALDI – Goldthorpe UK

Location: Goldthorpe, UK

View other products in the Commercial category

Project Overview

CONSTRUCTION CONTRACT

We provided the perimeter retaining walls to the entire perimeter of the warehouse to which the dock leveller pods were secured to plus external freestanding retaining walls and solid wall cladding to part of the development and the ground beams around the office area.

PROPORTION OF PROJECT UNDERTAKEN

We provided all of precast walls for the entire perimeter of the building, approx. 1000m of wall by max 2m high.

FUNCTION / ROLE

We provided the full design/coordination/detailing service for the precast elements from receipt of the Architects and Engineers drawings. Once this was done and approved by the Client we then manufactured the elements in our carousel factory, delivered them to site and installed the units. We also provided the erection crews, cranes and supervisors to control the erection to ensure programme and quality is met.

PRECAST ELEMENTS REQUIRED

150mm Solid Wall Ground Beam
300mm Twin Wall
325mm Twin Wall
200mm Twin Wall

VALUE

Value of firm’s commission/contract: €275K

Construction Contract value: €450M

DESIGN TEAM

Architect: Dalkin Scotton Ptrship Ltd

Engineer: Craddy Pitchers Davidson

GENERAL

Contracting Authority name : DSP Construction Management Ltd

Back to Projects