CONSTRUCTION CONTRACT
Two new sound stages were to be built and required precast panels to the lower 5m of the stage and for the complete perimeter. All panels had to achieve their required insulation U Value and the db rating because of their use.
PROPORTION OF PROJECT UNDERTAKEN
All perimeter precast insulated panels to the both sound stages.
FUNCTION / ROLE
We provided a full design/co-ordination/detailing service for the precast elements from receipt of the Architects and Engineers drawings. Once this was done and approved by the Client we then manufactured the elements in our carousel factory, delivered them to site to be fitted by a crew employed directly by the main contractor.
PRECAST ELEMENTS REQUIRED
300mm KC Wall
150mm Solid Wall
VALUE
Value of firm’s commission/contract: £400K
Construction Contract value: £10M
DESIGN TEAM
Architect: Sir Robert McAlpine (in house)
Engineer: Sir Robert McAlpine (in house)
GENERAL
Contracting Authority name: Sir Robert McAlpine