Project Overview

CONSTRUCTION CONTRACT

Two new sound stages were to be built and required precast panels to the lower 5m of the stage and for the complete perimeter. All panels had to achieve their required insulation U Value and the db rating because of their use.

PROPORTION OF PROJECT UNDERTAKEN

All perimeter precast insulated panels to the both sound stages.

FUNCTION / ROLE

We provided a full design/co-ordination/detailing service for the precast elements from receipt of the Architects and Engineers drawings. Once this was done and approved by the Client we then manufactured the elements in our carousel factory, delivered them to site to be fitted by a crew employed directly by the main contractor.

PRECAST ELEMENTS REQUIRED

300mm KC Wall

150mm Solid Wall

VALUE

Value of firm’s commission/contract: £400K

Construction Contract value: £10M

DESIGN TEAM

Architect: Sir Robert McAlpine (in house)

Engineer: Sir Robert McAlpine (in house)

GENERAL

Contracting Authority name: Sir Robert McAlpine